US grid interconnection queues

United States · energy · register

Requests to connect new generation and storage to the US grid, held by seven ISO/RTOs and ~50 balancing areas. A free annual research dataset covers 50+ operators under CC BY 4.0; commercial vendors sell daily updates over the same underlying queues.

Get this data

CSV · request JSON · request API · request

We build datasets in the order people request them. A request is a vote, and the count is public.

Where it lives

PublisherISOs, RTOs and transmission-owning utilities
Publication mandatenot established
LicenceMixed — PJM requires a redistribution licence and membership for commercial use; the LBNL compilation is CC BY 4.0 verified 2026-08-25
Access methodmixed
Fragmentation50+ operators
Update frequencyvaries; vendors sell daily
Free structured versionyes — https://emp.lbl.gov/queues
LBNL 'Queued Up', CC BY 4.0, annual. Data collection is led by the GridTracker team — the free file and the paid product share a pipeline.
Who else serves thisGridTracker / interconnection.fyi, Pearl Street Technologies (Enverus) (listed as caution, not endorsement — an existing free or commercial service is often the most useful thing on this page)

Legal screen

mandated publicationunknown
terms permissive or silentfail
no login paywall captcha personal datapass
no specialist legal advice neededfail
verdictfail

PJM prohibits redistribution of data 'or derived from' its systems without a licence, and commercial use requires membership. Richer fields sit behind a CEII tier requiring owner/operator authorisation.

Sources

Last checked 2026-08-25.

The clearest legal 'no' in this catalog, and worth reading as a worked example: an explicit derived-data restriction plus a statutory information tier.